AI Production Planning

See if the production plan is feasible,before you launch the order.

INVO analyzes planned orders, bills of materials, available lines, resources and the history of actual execution to predict completion time, production load and delay risk.

INVO — AI Production Planner · tomorrow's production

Units

24,850

Orders

186

Lines

7

Line 1Line 2Line 3
+45 min

Planned completion 14:20 Predicted completion 15:05

Delay risk78%

Assembly Line 3 · expected bottleneck

Recommendation

Move Batch #4821 to Line 2

Plan vs reality

The production plan doesn't always showhow production really runs.

The plan may assume the order finishes at 14:00. In practice the outcome depends on what happens on the floor: batch sizes, line load, job sequencing, staff availability and delays carried over from earlier stages.

INVO uses the history of actual production to estimate — before the shift even starts — how long production will likely take and where a problem may appear.

Plan

5 000 units

Start: 10:00
Planned completion: 13:00

Actual conditions

  • Line 3 heavily loaded
  • earlier order +18 min
  • bigger batch than usual
  • flight test close to full capacity

INVO forecast

Predicted completion

13:34

PlanPredicted completion
13:00
+34 min

Delay risk: 72%

The plan says what should happen. INVO uses historical data to predict what will most likely happen for real.

Before production starts

What can you knowbefore the shift begins?

  • When will production actually finish?

    Predicted completion time for the order and for the whole plan.

  • Which lines will be overloaded?

    Forecast utilization of the available capacity.

  • Where will a bottleneck appear?

    Processes likely to limit execution of the plan.

  • How many components will we actually use?

    An execution forecast that accounts for historical variances.

  • Which orders are at risk?

    Probability of missing the schedule.

  • Is the current staffing enough?

    Predicted staffing needs for individual stages.

How it works

From production history tothe next shift's forecast.

INVO uses data that already exists from planning and executing production. It compares earlier plans with actual execution and predicts how the next orders will run.

  1. Production history

    Plan + actual execution

  2. AI

    Finds the relationships

  3. Forecast

    What will likely happen tomorrow?

Plan
14:00
Forecast
15:05
Risk
78%
01

We collect real production data

INVO records, among others:

  • what we produced
  • how much
  • on which line
  • how long
  • at what throughput
  • what delays occurred

This builds a history of how production really ran — not just how it was planned.

02

AI finds recurring relationships

The models analyze earlier runs and check what influenced production time and throughput. For example, the system may notice:

At this production volume and flight-test load, similar orders took on average 12% longer than the plan assumed.

You don't have to define each such relationship by hand — the model finds them in the historical data.

03

We predict the next production run

When a new plan is created, INVO uses earlier data to estimate:

  • when production will finish
  • which lines may be overloaded
  • where a bottleneck may appear
  • which orders are at risk of delay

Instead of

Planned completion: 14:00

You also get

  • Predicted completion: 15:05
  • Delay risk: 78%
  • Problem: Line 3 overloaded

The more actual runs there are in the history, the more data we have to train and improve the predictive models.

Models & technology

Different questions requiredifferent models.

All the models draw on data collected in the INVO data warehouse. It combines the history of orders, bills of materials, production plans, line operation, actual execution times, component consumption, downtime and other events from ERP and MES.

On that basis we match the model to the specific question — for example how long production will take, where an overload will appear, or what the delay risk is.

Where do the models get data from?

ERPMESWMSProduction data

INVO Data Warehouse

  • Orders
  • Bills of materials
  • Production plans
  • Actual times
  • Line operation
  • Consumption
  • Downtime
  • Throughput

Plan

How production was planned

Actual

How it really ran

AI models

The data warehouse builds a history of how production was planned and how it really ran. That is the data we train and feed the predictive models on.

Forecasting model

How long will production actually take?

Models analyzing many factors

The model analyzes thousands of earlier runs and checks which conditions influenced their actual outcome.

It may notice, for example, that a certain combination of a large batch, a specific line and high load historically resulted in longer production.

When a similar order appears, it uses those relationships to predict its outcome.

Plan180 min
AI forecast214 min

Use cases

  • Production time
  • Delay risk
  • Predicted throughput
  • Component consumption

Benefit: A more realistic forecast based on actual runs.

Gradient Boosting

LightGBM · XGBoost · CatBoost

Time-series models

How will the situation change over time?

Models analyzing the course of production

These models don't only look at the final result. They analyze how load, production pace and other parameters change over the following hours.

That lets them predict at which point an overload or a drop in throughput will occur.

Line 3 · now

  • 82%
  • 10:3091%
  • 11:30103%
  • 12:30112%

Expected capacity overload

Use cases

  • Line load
  • Production pace
  • Future bottlenecks
  • Capacity utilization

Benefit: You see not only the current situation, but also the direction production is heading.

Time-Series Forecasting

N-HiTS · Temporal Fusion Transformer

Risk model

How high is the risk that the plan won't be met?

Models accounting for uncertainty

Production is not 100% predictable. That is why the model can show not only the most likely outcome, but also the range of possible outcomes and the level of risk.

Instead of one seemingly certain finish time, the planner sees how confident the forecast actually is.

Most likely finish
14:52
Expected range
14:40–15:10
Delay risk
84%

Use cases

  • Delay risk
  • Overload risk
  • Completion time range
  • Plan uncertainty assessment

Benefit: The planner decides based on a level of risk, not on a single seemingly certain number.

Probabilistic Forecasting

Quantile Regression · Conformal Prediction

And when the process is more complex?

With large volumes of data, many parallel lines, long operation sequences or data from IoT devices, we can also use neural networks and deep learning models. They allow more complex relationships to be analyzed, but we use them when tests show they improve forecast quality.

Neural Networks · Deep Learning · Sequence Models

A more complicated model does not always mean a better forecast.

We pick the model that best predicts actual execution on the client's own data.

Optimization engine

The model predicts a problem.The system helps find a better plan.

If the models predict that one of the lines will be overloaded, the next question is: what can we change?

The optimization layer can compare different ways of executing the plan, accounting for available lines, job sequencing, staffing, deadlines, changeovers and costs.

Current plan

15:12

Delay risk: 84%

AI forecast · Line 3 overloaded

Alternative scenarios

Scenario A

+4 employees

+$500

Additional cost

Finish
14:31

Scenario B

Recommended

Move 2 orders to Line 2

+$90

Additional cost

Finish
14:16

The forecast does not end with information about a potential problem. It can be used to compare variants and find a better way to execute the plan.

  1. ERP + MES + Production

  2. INVO Data Warehouse

    What did earlier runs look like?

  3. AI models

    What relationships exist in the data?

  4. Forecast

    What will likely happen tomorrow?

  5. Optimization

    What alternatives do we have?

  6. Recommendation

    Which variant gives the best predicted outcome?

From forecast to action

A forecast alone doesn't change production.A decision does.

  1. Alert

    Line 3 will likely exceed capacity by 12%.

  2. Recommendation

    Move two orders to Line 2.

  3. Simulation

    Check the impact of the change before you update the plan.

Current plan

As scheduled

15:12

Overtime: 72 min
Delay risk: 84%

Scenario A

+4 operators

14:31

Additional cost: $500
Delay risk: 21%

Scenario B · recommended

Move 2 orders

14:16

Additional cost: $90
Delay risk: 9%
See MES production

Business impact

A better plan before the start meansfewer costly corrections during the shift.

Overtime ↓

Fewer unplanned overtime hours

Waiting ↓

Less downtime and waiting

Throughput ↑

More output from the lines you already have

On-time ↑

Higher on-time delivery rate

Estimate the potential on your own production costs.

550,000 USD
300,000 USD
15%

Current avoidable cost: 850,000 USD

Savings potential

127,500 USD

/ year

≈ 10,625 USD / month

The simulation shows the potential scale of the effect and is not a guarantee of the result. The actual outcome depends on processes, data quality and the scope of the implementation.

Check whether tomorrow's plan is feasible,before production starts.

See how INVO can use the history of actual execution to predict production time, overloads and delay risk.